Environmental, Social and Economic Review Note (ESERN)



I. Project Overview

Identification

9320

Project Title

Increasing Investments in District Energy Systems in Cities – a SE4All Energy Efficiency Accelerator

Managing Division

Economy Division

Type/Location

Global

Region

Global

List Countries

Global

Project Description

Project Objective: The objective of this project is to assist developing countries and selected cities to accelerate their transition to lower-carbon and climate resilient societies through promoting modern District Energy Systems (DES).  

Estimated duration of project:

2017 - 2020 (36 Months)

Estimated cost of the project :

GEF Grant:              2,000,000

Co-finance:              9,711,774

Funding Source:GEF

II. Environmental Social and Economic Screening Determination

Summary of the Safeguard Risks Triggered

Safeguard Standard Triggered by the Project

Impact of Risk (1-5)

Probability of Risk (1-5)

Significance of Risk (L, M, H)*

SS 1: Biodiversity, natural habitat and Sustainable Management of Living Resources

1

1

L

SS 2: Resource Efficiency, Pollution Prevention and Management of Chemicals and Wastes

1

1

L

SS 3: Safety of Dams

1

1

L

SS 4: Involuntary resettlement

1

1

L

SS 5: Indigenous peoples

1

1

L

SS 6: Labor and working conditions

1

1

L

SS 7: Cultural Heritage

1

1

L

SS 8: Gender equity

1

1

L

SS 9: Economic Sustainability

1

1

L

Additional Safeguard questions for projects seeking GCF-funding (Section IV)

NA

NA

NA

*Refer to the UNEP ESES Framework (Chapter 2) and the UNEP’s ESES Guidelines


ESE Screening Decision

  • Low risk
  • Moderate risk
  • High risk
  • Additional information required


Development of ESE Review Note and Screening Decision


 ESERN Prepared by:Name: Ruth Coutto

Date: 14 October 2016

Conforms to ESES FrameworkName: Date:
Accepted by Project Manager: Name: Date:


 Recommended further action from the Safeguard Advisor