Environmental, Social and Economic Review Note (ESERN)




Excerpt
hiddentrue

Countries: Cambodia, Honduras, Kenya, Madagascar, Republic of Moldova, Papua New Guinea, Saint Lucia, Ukraine

Amount: US$ 9,000,000


I. Project Overview


Identification

Project Title

Integrated SC toolkit to improve the transmission of information under Articles 07 and 15

Managing Division

Economy Division

Type/Location

Global

Region

Latin America Caribbean, Africa, Europe, Asia Pacific

List Countries

Cambodia, Honduras, Kenya, Madagascar, Republic of Moldova, Papua New Guinea, Saint Lucia, Ukraine

Project Description

Estimated duration of project:

54 months

Estimated cost of the project :

GEF Grant:              2,000,000 USD

Co-finance:              7,000,000 USD


Funding Source:GEF


II. Environmental Social and Economic Screening Determination

Summary of the Safeguard Risks Triggered

Safeguard Standard Triggered by the Project

Impact of Risk (1-5)

Probability of Risk (1-5)

Significance of Risk (L, M, H)*

SS 1: Biodiversity, natural habitat and Sustainable Management of Living Resources

1

1

L

SS 2: Resource Efficiency, Pollution Prevention and Management of Chemicals and Wastes

1

1

L

SS 3: Safety of Dams

1

1

L

SS 4: Involuntary resettlement

1

1

L

SS 5: Indigenous peoples

1

1

L

SS 6: Labor and working conditions

1

1

L

SS 7: Cultural Heritage

1

1

L

SS 8: Gender equity

1

1

L

SS 9: Economic Sustainability

1

1

L

Additional Safeguard questions for projects seeking GCF-funding (Section IV)

NA

NA

NA

*Refer to the UNEP ESES Framework (Chapter 2) and the UNEP’s ESES Guidelines


ESE Screening Decision

  •  Low risk
  •  Moderate risk
  •  High risk
  •  Additional information required


Development of ESE Review Note and Screening Decision


 ESERN Prepared by:Name: Giovanna Chiodi MoireDate: 08 March 2017


Conforms to ESES FrameworkName: Yunae Yi
Date: 04 May 2017


Accepted by Project Manager: Name: Date:


 Recommended further action from the Safeguard Advisor

The project does not seem to have any major safeguard risks